Reliability starts
with every pipe.

Documented identity, verified condition and tracked service hours. Three requirements for releasing drilling tools to well operations.

Drill pipes on a prepared site — illustration
01

Identification

Match each tool to its passport, certificate and manufacturer’s marking.

02

Technical condition

Inspection, measurement and non-destructive testing before release. Defective tools stay out of service.

03

Traceability

Track service hours, inspections, repairs and transfers between wells.

TOOL RANGE AND CONFIGURATION

Drill pipe and drill collars

We select the well-specific tool package by dimensions, condition, connections and design loads. The table distinguishes documented tool specifications from configurations to be agreed in the well programme.

ToolOutside diameterGrade / connectionApplication
Drill pipe114.3 mm (4½ in)G105 · NC46Primary tool string*
Drill pipe (DP)127 mm (5 in)Grade and connection to be agreedConfiguration to the well programme
Drill pipe73.025 mm (2⅞ in)S135 · NC31Specifications of the documented batch
Drill collars165.1 / 203.2 / 228.6 mmPer the relevant passportSelection to the BHA programme
HWDP127 mm (5 in)1340 + 4137H · NC50BHA configuration to the well programme
Spiral drill collars / SDC247.65 mm (9¾ in)4145H · NC70BHA configuration to the well programme

* We select the primary 114.3 mm drill-pipe string according to well design, loads and drilling conditions. Where the project requires it, we provide a 127 mm (5 in) drill-pipe configuration; connection type, grade and quantity are agreed in the well programme.

MANDATORY FOR EVERY NGB PROJECT

NGB internal inspection and release procedure

This procedure applies to drill pipe, drill collars, heavy-weight drill pipe (HWDP), subs and BHA tools on every NGB project. Stricter manufacturer instructions or well-programme requirements take precedence.

What release to service means

Release is the responsible engineer’s documented decision that an identified tool may be used in the specified well and operating conditions. A manufacturer’s certificate establishes product specifications; release also requires a current condition assessment, compatible connections and a traceable service history.

The release file

Tool register + manufacturer documents + current inspection reports + BHA assembly list + service-hour log + written release decision.

  1. Identify every element

    Responsible
    The person responsible for tool records.
    Checks
    Match markings, item number, dimensions, grade and connection to the passport and certificate. For a batch certificate, establish the link between the individual pipe and the documented batch.
    Required evidence
    A register entry linked to the manufacturer’s documents.
    Hold / reject when
    Markings are unreadable, documents do not match the item, or its origin cannot be traced.
    Operating requirements

    Subs require documented material and origin; manufacture from previously used drill collars is not permitted.

    Technical basis

    Manufacturer documents establish product specifications. NGB matches them to each element’s markings and maintains the tool register.

  2. Inspect, measure and perform NDT

    Responsible
    A qualified independent NDT provider; the responsible engineer defines the inspection scope.
    Checks
    Before each well, check condition and dimensions and perform NDT in the required areas. Methods and acceptance criteria depend on the tool type. Inspection equipment requires documented calibration or setup verification.
    Required evidence
    A report identifying each element, date, methods, results and disposition.
    Hold / reject when
    A current report is missing, required inspection scope is incomplete, or results fail the acceptance criteria.
    Operating requirements

    NDT follows an agreed API / DS-1 programme for the tool type. Methods, inspection areas and rejection criteria are set before work begins.

    Technical basis

    The NDT programme follows API RP 7G-2, applicable DS-1 criteria and manufacturer instructions. Inspection before every well and the maximum intervals are mandatory NGB rules.

  3. Verify drill string and BHA compatibility

    Responsible
    The drilling engineer.
    Checks
    Check sizes, pin and box connections, subs, required lengths, permitted loads and operating limits of all elements, including rented tools.
    Required evidence
    An agreed BHA drawing and assembly list aligned with the well programme.
    Hold / reject when
    Connections are incompatible, specifications are unverified, or loads exceed permitted limits.
    Operating requirements

    Keep the BHA drawing and sketches with outside diameter, inside diameter and length. Sub working length must be at least 1.5 times the bore diameter and meet the minimum in the agreed drawing; select bit subs for the specific bit. Spiral integral-blade stabilizers must be 1/8–1/16 inch under nominal, according to size; full-gauge stabilizers are not accepted. At the rig, verify three working Top Drive subs, six lifting caps and six lifting subs for each required drill-collar diameter, at least two safety clamps and two spare drill-collar joints of each size. The assembly list defines additional accessible reserves and required subs.

  4. Protect connections in transit and storage

    Responsible
    The person responsible for transport or storage, and the receiving person at the rig.
    Checks
    Check thread and shoulder cleanliness and signs of impact or corrosion. Fit suitable, serviceable protectors to both pin and box ends. Store tools on supports clear of the ground.
    Required evidence
    A receiving-inspection entry, with damage recorded separately.
    Hold / reject when
    Dirt, corrosion or damage is present, or a connection has not been checked after losing its protection.
    Operating requirements

    Every receiving inspection checks both connection ends and protectors; missing protection requires re-inspection.

    Technical basis

    Cleanliness, thread protection and storage follow the specific tool manufacturer’s instructions and NGB receiving procedures.

  5. Prepare and control connection make-up

    Responsible
    The rig crew under the responsible specialist’s supervision.
    Checks
    Clean and inspect threads and shoulders before make-up; use the specified thread compound. Set make-up torque from manufacturer instructions and the work programme, and verify it with equipment having documented calibration.
    Required evidence
    Assembly settings and control records, plus evidence that measurement equipment is fit for use.
    Hold / reject when
    Compound or torque is unspecified, measurement is unreliable, or a connection is damaged or makes up incorrectly.
    Operating requirements

    For drill collars and HWDP, verify make-up at the contractor’s base with a Torque Master-type hydraulic wrench and record actual torque in the passport. Compound requires a quality document and must meet the connection manufacturer’s requirements.

  6. Track service history and inspection intervals

    Responsible
    The person responsible for tools at the rig.
    Checks
    Record hours by operation type, wells, inspections, repairs and replacements. Schedule the required action before the 600 / 400 / 800-hour limits in the control chart below. Any shorter prescribed interval takes precedence.
    Required evidence
    A service record or log, NDT and pressure-test reports, and sub-replacement entries.
    Hold / reject when
    History is incomplete, an inspection is due, or the required inspection or replacement is undocumented.
    Operating requirements

    After every five bit runs, rotate working drill-collar connection positions and check make-up of non-working connections; interchange working and non-working drill-pipe and HWDP connections monthly. Drill-pipe test pressure is 1.5 times maximum working pressure, at least 25 MPa to 4,000 m and 30 MPa below 4,000 m, under a technical programme compatible with the tool set and test equipment ratings. If the required test exceeds those ratings, hold the set until the programme is resolved.

    Technical basis

    The 600 / 400 / 800-hour limits are set by NGB’s internal procedure. Stricter manufacturer or work-programme requirements take precedence.

  7. Reassess after an abnormal event

    Responsible
    The rig supervisor reports the event; the responsible engineer determines additional inspection.
    Checks
    Stop using a suspect element after overload, impact, suspected washout or damage. Assess it before running again, regardless of the hours remaining until scheduled inspection.
    Required evidence
    An event record and an additional assessment report.
    Hold / reject when
    The cause remains unresolved or suitability for continued operation is unconfirmed.
    Operating requirements

    After cutting or repairing threads on subs, drill collars or HWDP, repeat NDT before return to service.

    Technical basis

    Additional inspection follows suspected damage, overload, repair or thread cutting, before returning the tool to service.

  8. Segregate defects and document re-release

    Responsible
    The tool custodian segregates the item; the authorized engineer decides on its return.
    Checks
    Mark and separate defective, overdue or untraceable tools. After an authorized repair or resolution of the hold reason, require re-inspection before return to the operating set.
    Required evidence
    A nonconformance record, repair documents where applicable, an acceptable inspection report and written release.
    Hold / reject when
    The cause remains unresolved, acceptance criteria are unmet, or written release is missing.
    Operating requirements

    Replace drill collars according to actual condition and inspection results. The 400-hour limit concerns replacement of subs in the BHA, not automatic disposal of drill collars.

    Technical basis

    Physical segregation, a traceable record and written re-release are mandatory. Rejection criteria are specified for the individual tool.

Mandatory NGB inspection intervals

Non-destructive testing

600 hours

For drill pipe, BHA subs and drill collars: before each well and at intervals not exceeding 600 hours of drilling and reaming.

BHA subs: replacement

400 hours

Replace subs in the BHA at intervals not exceeding 400 hours. Inspection determines their suitability for further use.

Pressure testing

800 hours

Drill pipe: before work starts and at intervals not exceeding 800 hours of drilling, reaming, hole opening and gauging operations.

These intervals are NGB internal operating limits. A shorter interval required by the manufacturer, the well programme or the actual condition takes precedence. Each inspection, test and replacement is recorded against the identified tool.

TECHNICAL FRAMEWORK

Technical standards and manufacturer instructions

We use the relevant API standards, DS-1 inspection criteria and manufacturer instructions to define product requirements, connection checks and inspection methods. The well programme records the applicable edition and acceptance criteria.

API Spec 5DP
Drill pipe — product specifications.
API Spec 7-1
Manufacturing requirements for applicable rotary drill stem elements.
API Spec 7-2
Threading and gauging of rotary shouldered connections.
API RP 7G-1
Drill stem and connection properties; applicable technical basis for engineering selection.
API RP 7G-2
Inspection and classification of used drill stem elements.
DS-1
Inspection requirements for drill stem elements; the programme defines the applicable category, methods and acceptance criteria.

API — official standards catalogue

BHA CONFIGURATION

The right tools for the well programme

We rent calibrators / stabilizers (KLS) from DENIMEX Ukraine (DENIMEX UKRAINE LLC). Selection follows the well programme. The supplier is responsible for servicing its rented tools.

NGB performs incoming acceptance: match the passport and serial number, review service and inspection reports and operating-hour records, inspect the tool and verify BHA compatibility. Only a documented, suitable tool is released to the well.

Cooperation with DENIMEX UKRAINE LLC for tool rental and servicing is governed by Framework Agreement No. 2611-24 of 26 November 2024. Addendum No. 5 documents the parties’ cooperation.

DENIMEX repair and maintenance centreStabilizer regrinding

Download Addendum No. 5 (PDF)

DOCUMENT LIBRARY

Certificates and records

Manufacturer certificates and passport documents for reviewing tool specifications and identity. These documents do not replace a current pre-well inspection report.

01 / PDF

Drill pipe 2⅞ in, S135, NC31 — factory quality package

Taizhou Elite Drilling Pipe Co., Ltd. Factory documentation; S135, NC31. Original documented batch: 429 pieces, 4130.06 m. Includes factory tests and quality checks.

Download PDF7 p. · 2.15 MB
02 / PDF

Drill pipe 4½ in, G105, NC46 — factory quality package

Taizhou Elite Drilling Pipe Co., Ltd. Factory documentation; G105, NC46. Original documented batch: 484 pieces, 4618.45 m. Includes factory tests and quality checks.

Download PDF6 p. · 1.70 MB
03 / PDF

Drill pipe 114.3 mm, G105, NC46 — passport copy

Taizhou Elite Drilling Pipe Co., Ltd. Factory documentation; G105, NC46. Original documented batch: 484 pieces, 4618.45 m. Copy for the same batch.

Download PDF3 p. · 1.68 MB
04 / PDF

Drill pipe 73.025 mm, S135, NC31 — passport copy

Taizhou Elite Drilling Pipe Co., Ltd. Factory documentation; S135, NC31. Original documented batch: 429 pieces, 4130.06 m. Copy for the same batch.

Download PDF3 p. · 1.68 MB
05 / PDF

Spiral drill collars 6½ in, NC46 — quality documentation

Jiangsu Shuguang Huayang Drilling Tool Co., Ltd. Factory documentation; 4145H, NC46. Original documented batch: 12 pieces, 114.535 m. Includes factory tests and quality checks.

Download PDF27 p. · 0.50 MB
06 / PDF

Spiral drill collars 8 in, 6⅝ FH — quality documentation

Jiangsu Shuguang Huayang Drilling Tool Co., Ltd. Factory documentation; 4145H, 6 5/8 FH. Original documented batch: 3 pieces, 28.28 m. Includes factory tests and quality checks.

Download PDF9 p. · 0.40 MB
07 / PDF

Spiral drill collars 9 in, 6⅝ FH — quality documentation

Jiangsu Shuguang Huayang Drilling Tool Co., Ltd. Factory documentation; 4145H, 6 5/8 FH. Original documented batch: 6 pieces, 57.442 m. Includes factory tests and quality checks.

Download PDF15 p. · 0.44 MB
08 / PDF

HWDP 127 × 76.2 mm

Outside / inside diameter: 127 × 76.2 mm. Steel: 1340 + 4137H. Connection: NC50.

Download PDF8 p. · 0.46 MB
09 / PDF

Spiral drill collars / SDC 247.65 × 76.2 mm

Outside / inside diameter: 247.65 × 76.2 mm. Steel: 4145H. Connection: NC70.

Download PDF6 p. · 0.44 MB

The library includes factory documents from 2016–2017 and additional packages dated 2026. Date of manufacture and current fitness for use are different matters: operational release requires assessment of the actual condition and service history.